Toyota 4Runner manuals

Toyota 4Runner: Installation

INSTALLATION

PROCEDURE

1. INSTALL STEERING WHEEL ASSEMBLY

(a) Align the matchmarks on the steering wheel assembly and steering main shaft assembly.

(b) Install the steering wheel assembly set nut.

Torque:

50 N·m {510 kgf·cm, 37 ft·lbf}

2. INSTALL CRUISE CONTROL MAIN SWITCH


3. INSTALL STEERING PAD SWITCH ASSEMBLY

(a) Attach the 2 claws and 4 guides to install the steering pad switch assembly.

(b) Install the 4 screws.

Torque:

2.4 N·m {24 kgf·cm, 21 in·lbf}

(c) Connect the connector.

4. INSTALL STEERING PAD


5. INSTALL NO. 2 STEERING WHEEL LOWER COVER


6. INSTALL NO. 3 STEERING WHEEL LOWER COVER


7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:

When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See page ).


8. CHECK SRS WARNING LIGHT

(See page )


Inspection
INSPECTION PROCEDURE 1. INSPECT STEERING PAD SWITCH ASSEMBLY (a) Inspect the steering pad switch assembly. (1) Disconnect the switch connector. Text in Illustration *1 Up ...

Steering Gear / Linkage
...

Other materials about Toyota 4Runner:

Installation
INSTALLATION PROCEDURE 1. INSTALL PROPELLER SHAFT ASSEMBLY (a) Align the matchmarks on the propeller shaft flange and differential flange. (b) Install the propeller shaft assembly with the 4 washers, 4 bolts and 4 nuts. Torque: 88 N·m {899 kgf·cm, 65 ...

Removal
REMOVAL PROCEDURE 1. TABLE OF BOLT, SCREW AND NUT HINT: All bolts, screws and nuts relevant to installing and removing the instrument panel are shown along with their alphabet code in the table below. 2. DISCONNECT CABLE FROM NEGATIVE BATTERY TERMINAL ...

© 2016-2021 | www.to4runner.net

0.0058