INSTALLATION

PROCEDURE

1. INSTALL TRANSFER ASSEMBLY

(a) Install the transfer to the transmission.

(b) Install the 8 bolts.

Torque:

24 N·m {245 kgf·cm, 18 ft·lbf}

2. INSTALL AUTOMATIC TRANSMISSION ASSEMBLY

(a) Install the automatic transmission (See page ).


3. ADD TRANSFER OIL


4. CHECK FOR TRANSFER OIL LEAK

Reassembly
REASSEMBLY PROCEDURE 1. INSTALL TRANSFER DRIVE SPROCKET SUB-ASSEMBLY Text in Illustration *1 Shifting Key *2 Drive Sprocket *3 ...

Transfer Case Front Oil Seal
Components COMPONENTS ILLUSTRATION Replacement REPLACEMENT PROCEDURE 1. DRAIN TRANSFER OIL 2. REMOVE FRONT PROPELLER SHAFT ASSEMBLY (a) Remove the front propeller shaft (See page ). ...

Other materials about Toyota 4Runner:

On-vehicle Inspection
ON-VEHICLE INSPECTION PROCEDURE 1. INSPECT PARK/NEUTRAL POSITION SWITCH ASSEMBLY (a) Apply the parking brake and turn the ignition switch on (IG). (b) Depress the brake pedal and check that the engine starts when the shift lever is in N or P, but does no ...

System Diagram
SYSTEM DIAGRAM Communication Table Sender Receiver Signal Line Combination meter assembly Main body ECU (Multiplex network body ECU) Vehicle speed signal CAN ...

© 2016-2024 | www.to4runner.net

0.0085